Start Time & Calculated Column Wonkiness in a SharePoint Event Calendar

Posted by _zekeMouseOver on ASP.net Weblogs See other posts from ASP.net Weblogs or by _zekeMouseOver
Published on Tue, 11 May 2010 20:02:00 GMT Indexed on 2010/05/11 20:55 UTC
Read the original article Hit count: 267

Filed under:

I was creating some custom rollups on some of our event calendars and came across a very odd bug when trying to grab only the date component of the built-in Start Time field. One's first inclination will be to create a calculated column and give it the formula...

 =[Start Time]

... and then assign its output type to be "Date Only." This works well until a user adds an All Day Event. For reasons unexplainable, the All Day Event flag causes your =[Start Time] to display the date minus one day. Here is an example of this in action:

 

Start Date and Time, Duration, Start Date Value and Start Day are all calculated fields. Notice how the Start Date and Time (=[Start Time]) is reporting 6:00PM of the previous day. The Start Date Value (=[Start Time] - Output Type: Number) confirms this (.75 = 6:00 PM.) Curiously enough, the Duration (=[End Time]-[Start Time]) is properly reporting the duration between 12:00AM and 11:59PM. Why? I don't know. Perhaps it's somehow bound to the regional settings on the site, but I'm not interested in changing a global site setting for the sake of one calculated field.

With this information at our disposal, our calculated column to display the date part of the start date needs to be modified to add one day to the [Start Time] field if an All Day Event is selected. To determine this, we use the Duration above to assume the item is an all-day event and change our formula to be:

=IF(TEXT(([End Time]-[Start Time])-TRUNC(([End Time]-[Start Time]),0),"0.000000000")="0.999305556",[Start Time] + 1, [Start Time])

This will work, but what happens when the user de-selects the "All Day Event" checkbox? The duration stays the same, but all other values begin reporting the correct time:

 

Since our formula above is strictly based on an expected duration, it will add one to the correct date, causing the date 5/11/2010 to appear. Notice though that the raw value of the start time (in this case) is a non-fractional number (40,308) whereas the all-day event was being represented as 6:00 PM (.75) of the previous day. We can use this to add one more nested branch of logic to our calculation:

=IF(TEXT(([End Time]-[Start Time])-TRUNC(([End Time]-[Start Time]),0),"0.000000000")="0.999305556",IF([Start Time]=ROUND([Start Time],0),[Start Time],[Start Time]+1),[Start Time])

I feel somewhat... dirty about having to resort to this kind of calculation in what SHOULD have been a simple =[Start Time] to extract the date part of the Start Time field, but there you have it. Make sure to shower extra longer after having used it.

© ASP.net Weblogs or respective owner

Related posts about sharepoint